Works in the Biology Department are progressing well and one hopes that the works concerning the M&E works will be completed in the coming weeks. During the summer months all the tiling works, electrical, plumbing, fire, IT and AC works were completed. Furthermore, pipework connecting the labs to the facilities located on the roof is ongoing. All new windows have been installed and all plastering is practically completed, whereas gypsum works are being finalised. Soffits for all offices have been completed.
Currently gas pipes are being installed and finishing of the IT network connections and testing is taking place.
In the coming weeks, painting of the completed areas will start together with the installation of the doors, ventilation grills, remaining soffit and fume cupboard ducting system. Meanwhile, the tender for the office furniture needs to be re-issued whereas, the AV tender and lab furniture one are being evaluated.